The photos from the Public Safety Complex construction site are becoming increasingly dramatic. This week, Renascent crews are tackling the demolition of the last part of the Central Wing patient tower.
The City is investing $40 million to transform the vacated St. Mary's Hospital site in North Knoxville into a new Public Safety Complex, which will house Police, Fire, City Court and Pension System operations. The investment improves City efficiency, but it also protects the neighborhood from the unused site becoming blighted.
The City also is investing $6.5 million to raze unneeded old buildings on the northern end of the hospital campus that can't be repurposed. The iconic 1929 Building is being preserved. The plan is for that half of the property to eventually be privately redeveloped.
Lincoln Memorial University is converting the Magdalen Clarke Tower into classrooms.
Meanwhile, here's a rundown of other work happening on the construction site this week:
Environmental Abatement Inc. is completing removal of equipment from the top floor of the Professional Office Building while also working on the fourth floor and pulling light fixtures from the stairwells.
Pictured here is the first floor of the Women's Pavilion, where EAI was working last week.
In addition to taking down the C-Wing patient tower, Renascent this week will be doing demolition work in the Annunciation Wing and continuing to sort and remove debris.
NEO Corp. crews will continue abatement work in the St. Joseph Wing.
Posted by
evreeland
On 18 August, 2020 at 10:15 AM
Recent Posts
Public Safety Complex Move-in to Begin in January
Welcome, Neighbor! LMU Opens College of Dental Medicine, Clinic Next to City Public Safety Complex
Crews to Repair Original Brick Façade at Public Safety Complex
Week 125: Heading into Long Final Home Stretch
Week 110: Work Progressing in All 3 Buildings, Plus Walls Going Up at New Court Building
Week 109: Check Out the Progress with City Court Construction
Week 100: Public Safety Complex is Two-Thirds Completed!
Week 97: Drywall going up!
Week 93: More Interior Walls Going Up
City, County Moving Ahead With Behavioral Health & Urgent Care Facility Next to Safety Complex
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
Safety Complex
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts