Welcome to the City Communications update page on the approximate $70 million transformation of the former St. Mary’s Hospital campus into a new complex for the Police and Fire Departments, E911, Pension System offices and City Court operations.
Visit here for regular updates, photos and videos on the project, as well as information on Lincoln Memorial University's $40 million investment in new nursing and dental schools at the site.
The City's new safety complex is scheduled to be substantially completed by late 2022, with staff move-ins to follow incrementally. Learn more at
www.knoxvilletn.gov/safetycomplex
.
Recent Posts
1
2
3
4
5
6
Week 91: New Interiors for 3 Repurposed Buildings, Footers Poured for New Court Building
Two very different things are happening right now at the former St. Mary's Hospital site in North Knoxville as it transitions toward its next life as the City's Public Safety Complex. No. 1, an arr ...
more»
Posted by
evreeland
On Nov 18, 2021 at 2:56 PM
Week 59: Grading the Public Safety Complex Grounds
This week, tons of pulverized debris are being graded into place on the grounds of the City's Public Safety Complex - a process that is both economical and environmentally sound. With the grading, ...
more»
Posted by
evreeland
On Apr 07, 2021 at 12:23 PM
Week 56: Concrete Foundation Walls Formed, Poured
Lots of concrete began to pour on the last weekday in February. Crews with Al Blankenship Enterprises have continued since then, forming and pouring new foundation walls at the City's Public Safety ...
more»
Posted by
evreeland
On Mar 15, 2021 at 11:39 AM
Week 54: Pouring Concrete - Lots of It
The last weekday in February was nicknamed "Pour Day," because that was the day when Al Blankenship Enterprises employees poured 100 cubic yards of concrete. A hundred yards - that's the length of ...
more»
Posted by
evreeland
On Mar 04, 2021 at 12:41 PM
Coming Soon: Peaceful Green Space at Center of Public Safety Complex
For the past year, the images you've seen from the Public Safety Complex reconstruction site in North Knoxville have mostly been of demolition - obsolete St. Mary's Hospital buildings coming down, or ...
more»
Posted by
evreeland
On Mar 02, 2021 at 3:51 PM
Week 52: Foundation Wall Going Up
This week, more new foundation wall is taking shape where a new City Court courtroom will be built. Al Blankenship Enterprises formed this section of wall and poured concrete (below). The work crew ...
more»
Posted by
evreeland
On Feb 19, 2021 at 10:19 AM
Week 51: Preserving the 1929 Building, Constructing a Wall and Removing Debris
Heading into mid-February, a lot of different tasks are underway at the Public Safety Complex reconstruction site in North Knoxville - some additions (a new foundation wall), and some subtractions (go ...
more»
Posted by
evreeland
On Feb 11, 2021 at 5:13 PM
Week 49: New Foundation, Big Debris, Protecting the 1929 Building
This week at the Public Safety Complex reconstruction site, crews with Al Blankenship Enterprises are working on the east and west end footers at the Central Wing Annex, tying in rebar. Below-grade ...
more»
Posted by
evreeland
On Jan 27, 2021 at 6:05 PM
Week 48: Foundation Walls of Razed Annunciation Wing Now Being Demolished
Last year, the obsolete Annunciation Wing of the vacated St. Mary's Hospital in North Knoxville was leveled. Now, Renascent contractor crews have begun demolishing the tall foundation walls that once ...
more»
Posted by
evreeland
On Jan 22, 2021 at 10:16 AM
Week 47: Masons Repair Parapet Atop 1929 Building
More TLC continues to be given to the beloved 1929 Building, the original marble-accented St. Mary's Hospital building in North Knoxville that's being preserved by the City. The restoration of the 92- ...
more»
Posted by
evreeland
On Jan 15, 2021 at 9:41 AM
1
2
3
4
5
6
Recent Posts
Public Safety Complex Move-in to Begin in January
Welcome, Neighbor! LMU Opens College of Dental Medicine, Clinic Next to City Public Safety Complex
Crews to Repair Original Brick Façade at Public Safety Complex
Week 125: Heading into Long Final Home Stretch
Week 110: Work Progressing in All 3 Buildings, Plus Walls Going Up at New Court Building
Week 109: Check Out the Progress with City Court Construction
Week 100: Public Safety Complex is Two-Thirds Completed!
Week 97: Drywall going up!
Week 93: More Interior Walls Going Up
City, County Moving Ahead With Behavioral Health & Urgent Care Facility Next to Safety Complex
Group Blogs
City Blog
KAT Blog
KPD News & Alerts
Magnolia Avenue Streetscapes Project
More...
Post Categories
Safety Complex
Content Alert Subscription
Blog Feeds
Podcast Feeds
Subscribe to Email Alerts